Construction update: Axia greenhouse in full swing Share this post facebook twitter whatsapp linkedin The construction of the new greenhouse at Axia is progressing steadily. “Last week, the first steel structure was successfully installed,” says Wouter Omvlee, project manager at Certhon. “After starting work in the second week of this year, beginning with excavation and the installation of the rainwater drainage system, construction is now moving ahead rapidly.” The plan is to complete the substructure within three weeks. After that, we will begin glazing the greenhouse and installing the sandwich panels. Certhon aims to have the greenhouse fully enclosed by the end of February, allowing us to start digging the trenches in the water technical area. We look forward to the progress of this project and will keep you updated on the next developments.