Moving into the next phase Share this post facebook twitter whatsapp linkedin Recent weeks have marked significant progress at the Axia demonstration greenhouse. The installation of the screening systems, lifting installation and heating system at greenhouse level have now been completed, marking the successful completion of another major construction phase. Current activities are focused on the remaining excavation works inside the greenhouse. These preparations are essential for the next stages of the project and will support the installation and commissioning activities that follow. Focus on groundwork and commissioning Over the coming weeks, the internal groundwork will be completed, after which concrete works will begin. The project team will then continue with commissioning the various greenhouse systems, ensuring all installations are prepared for operational use.